
|
 |

First Quarter 2010Agitated Leach Plant
Detailed engineering is in process for the agitated leach plant modifications and some elements are being tested for installation. Costs estimates are approximately $3.0 million to confirm and test the changes required. Proposals for additional crushing and screening equipment are under review. There may be additional purchase costs for equipment once testing is complete. The agitated leach plant is expected to be fully operational in 2011. When fully operational, the agitated leach plant is expected to increase iodine production capacity to 1,500 tonnes per year.
read more... Production Results
Selected operational information for Aguas Blancas mine for the three months ended March 31, 2010 compared to 2009 is set out in the following table:
| |
Three Months Ended March 31, 2010 |
Three Months Ended March 31, 2009 |
| Tonnes Mined (Mt) |
929,127 |
1,037,490 |
| Iodine Grade (ppm) |
621 |
549 |
| Iodine Produced (Mt) (000’s) |
315 |
246 |
| Iodine Sold (Mt) (000’s) |
317 |
199 |
Tonnage mined in the first quarter of 2010 was slightly lower than the same period in 2009 due to lower productivity by one of the continuous mining machines. This was more than compensated for however by an increase in grade of ore mined.
The optimization and modifications implemented in the latter part of 2009 that positively affected production continued to favorably impact production in the first quarter of 2010, culminating in the second highest quarterly production and sales for the Company, nearly equaling fourth quarter 2009. Disciplined maintenance planning and execution are also an integral part of the increased production realized.
Salvador Potash Project -- Brazil
The Company holds exploration permits covering an area of 2,500 square kilometers over the southern on-shore portion of the Reconcavo sedimentary basin. Historical drilling records indicate the occurrence of potash beds at depths of approximately 1,000 meters, directly overlying the halite salt bed located in the evaporitic section of the lower Alianca Formation of upper Jurassic age.
0The Salvador project is located near the city of Salvador, Bahia, on the northeastern coast of Brazil, and is located within the large on-shore Reconcavo sedimentary basin with the potential to host a major new potash deposit. During 2009, the Company carried out geophysics and geological work for the selection and permitting of drill targets. In December 2009, the Company commenced the first phase of a drill program comprising of three holes, designed to define the depth, thickness and grade of the potash beds within the central portion of its Salvador Potash Project. Drilling on the first hole advanced slowly during the first quarter. Due to heavy rains and issues with the drill rig, the first hole is now expected to be completed in the third quarter of 2010. Geological indicators are still positive in this hole and the Company is optimistic about encountering the zone of interest in the coming 300 to 500 meters of drilling. Drilling of a second hole recently commenced and is currently at a depth of over 300 meters.
Year End 2009New Management
As of December 1, 2009, Mr. Tim Miller was appointed President and Chief Executive Officer and has joined the Board of Directors of the Company. Mr. Miller was most recently Vice President Central and South America for Goldcorp Inc. where he was responsible for all of Goldcorp's activities in Central America, South America and the Caribbean. Prior to that, Mr. Miller spent many years with Glamis Gold Ltd. as Vice President and Projects Manager for their Central American operations. His background also includes construction and management of major heap leach and agitated leach operations throughout South and Central America. Mr. Miller has a BSc. Chemistry from the University of New Mexico and an MBA from Webster University.
read more... Agitated Leach Plant
During 2009, the Company continued to work with its independent consultant on analyzing various
possible solutions for the crushing/grinding circuit of the agitated leach plant. In March 2010, the
Company decided on a fine crushing and screening system, which are anticipated to rectify the problems
with the agitated leach plant. The cost of this system is estimated at $2.8 million and is expected to be
completed within twelve months. When fully operational, the agitated leach plant is expected to increase
iodine production capacity to 1,500 tonnes per year.
Production Results
Selected operational information for Aguas Blancas mine for the three months and year ended
December 31, 2009 compared to 2008 is set out in the following table:
| |
Three Months Ended December 31, 2009 |
Three Months Ended December 31, 2008 |
Year Ended December 31, 2009 |
Year Ended December 31, 2008 |
Tonnes Mined (Mt) |
847,345 |
1,050,299 |
3,203,373 |
2,592,083 |
Iodine Grade (ppm) |
633 |
595 |
570 |
659 |
Iodine Produced (Mt) (000's) |
318 |
203 |
1,096 |
844 |
Iodine Sold (Mt) (000's) |
338 |
205 |
1,086 |
861 |
Tonnage mined was increased in 2009 compared to 2008 in order to compensate for lower ore grades and to increase overall iodine production.
Iodine production for 2009 has improved from 2008 not only from increased tonnes mined but also due to heap leach optimization with increased solutions flows. It was also favorably impacted by the reactivation of leached pads by ripping and re-leaching. In the plant, a major focus on blow-out tower maintenance has improved recoveries and throughput to the plant. Optimization of the fusion plant through some minor modifications improved quality and utilization of the plant. During the colder months, the use of a heater to maintain temperatures of the brine also increased operating time and throughput at the blow-out towers.
Salvador Potash Project - Brazil
The Salvador project is located near the city of Salvador, Bahia, on the northeastern coast of Brazil, and is located within the large on-shore Reconcavo sedimentary basin with the potential to host a major new potash deposit. During 2009, the Company carried out geophysics and geological work for the selection and permitting of drill targets. In December 2009, the Company commenced the first phase of a drill program comprising of three holes, designed to define the depth, thickness and grade of the potash beds within the central portion of its Salvador Potash Project. Drilling on the first hole started slowly with completion now expected in the second quarter of 2010. The first hole is expected to be drilled to a depth of 1,500 metres.
The Company holds exploration permits covering an area of 2,500 square kilometers over the southern on-shore portion of the Reconcavo sedimentary basin. Historical drilling records indicate the occurrence of potash beds at depths of approximately 1,000 meters, directly overlying the halite salt bed located in the evaporitic section of the lower Alianca Formation of upper Jurassic age.
Third Quarter 2009Agitated Leach Plant
During the third quarter of 2009, the Company continued to work with its independent consultant on analyzing various possible solutions for the crushing/grinding circuit of the agitated leach plant. Further analysis of the ore feed characteristics resulted in proposed modifications, which management is currently studying to determine the proper course of action. When fully operational, the agitated leach plant is expected to increase iodine production capacity from 1,000 tonnes per year to 1,500 tonnes per year.
read more... Production Results
Selected operational information for Aguas Blancas mine for the three and nine months ended September 30, 2009 is set out in the following table:
| |
Three Months
Ended
September
30, 2009 |
Three Months
Ended
June
30, 2009 |
Three Months
Ended
September
30, 2008 |
Nine Months
Ended
September
30, 2009 |
Nine Months
Ended
September
30, 2008 |
Tonnes Mined (Mt) |
707,664 |
581,038 |
560,632 |
2,356,028 |
1,541,784 |
Iodine Grade (ppm) |
544 |
436 |
696 |
548 |
703 |
Iodine Produced (Mt) (000's) |
285 |
247 |
178 |
778 |
641 |
Iodine Sold (Mt) (000's) |
269 |
281 |
213 |
748 |
656 |
Tonnes of ore mined improved during the third quarter of 2009 from the second quarter of 2009 as additional equipment was brought in to rectify production shortfalls due to mine contractor's equipment downtime and re-handling of ore due to pad problems in the second quarter. Consistent with the current mine plan, the iodine grade increased in the third quarter.
As expected, iodine production during the third quarter of 2009 has improved from the second quarter of 2009 due to warmer weather and heap leach optimization with increased solutions flows.
The Company expects iodine production to slightly increase for the remainder of the year due to heap leach optimization and delivery of more ore to the leach pads.
Salvador Potash Project -- Brazil
During the quarter ended September 30, 2009 the Company continued to pursue the environmental permits for drilling on its Salvador Potash Project. The Salvador project is located near the city of Salvador, Bahia, on the northeastern coast of Brazil. In late October the environmental permits were granted. The Company expects to commence the first phase of the drill program, designed to define the depth, thickness and grade of the potash beds within the central portion of the project area, in the latter part of November, 2009. The Salvador project is located within the large on-shore Reconcavo sedimentary basin with the potential to host a major new potash deposit in Brazil.
The Company holds exploration permits which have been recently expanded to cover an area of 2,500 square kilometers over the southern on-shore portion of the Reconcavo sedimentary basin. Historical drilling records indicate the occurrence of potash beds of various meters in thickness at depths of approximately 1,000 meters, directly overlying the halite salt bed located in the evaporitic section of the lower Alianca Formation of upper Jurassic age.
Second Quarter 2009Agitated Leach Plant
During the first half of 2009, the Company installed modifications to the crushing/grinding system of the agitated leach plant based on recommendations provided by independent consultants. During the startup and testing of these modifications additional problems were encountered. As a result, a more in depth analysis of the ore feed characteristics and possible additional modifications to the crushing/grinding system are required to resolve the material processing problems.
When fully operational, the new agitated leach plant is designed to increase production capacity from
1,000 tonnes of iodine per year to 1,500 tonnes per year.
read more... Production Results
Selected operational information for Aguas Blancas mine for the six months ended June 30, 2009 is set out in the following table:
| |
Three months ended June 30, 2009 |
Three months ended March 31, 2009 |
Three months ended June 30, 2008 |
Six months ended June 30, 2009 |
Six months ended June 30, 2008 |
Operations |
|
|
|
|
|
Tonnes Mined metric tonnes (Mt) |
581,038 |
1,037,490 |
530,055 |
1,618,528 |
981,152 |
Iodine Grade (ppm) |
436 |
549 |
734 |
508 |
706 |
Iodine Produced (Mt) |
247 |
246 |
220 |
493 |
463 |
Iodine Sold (Mt) |
281 |
199 |
230 |
480 |
443 |
Tonnes of ore mined during the second quarter of 2009 were lower than the first quarter of 2009 mainly as a result of re-handling of ore due to pad operation problems and mine contractor's equipment downtime. Measures are being taken to rectify production shortfalls due to equipment downtime by bringing in additional mining equipment. Consistent with the current mine plan, the iodine grade declined in the current quarter and is expected to increase again for the second half of 2009.
Iodine production during the second quarter of 2009 was comparable to the first quarter of 2009 but was affected by seasonal winter conditions and pad operation problems. In addition, during the first half of 2009, iodine production was favorably impacted by the reactivation of leached pads by ripping and releaching.
Nitrate Fertilizer Project
The Company has temporarily deferred the development of the nitrate fertilizer plant due to the global credit crisis, the need to preserve cash and to focus on resolving the technical issues on the agitated leach plant.
During the second quarter, the Company made other changes to the design and construction of the leach pads to improve iodine production. The Company expects iodine production to increase for the remainder of the year from heap leach optimization and as the warm weather arrives.
Salvador Potash Project -- Brazil
The Company expects to commence drilling upon receipt of environmental permits, which are anticipated to be received late in the third quarter or early fourth quarter of 2009. Drill sites have been selected based on historical drill results and studies of geophysical and geological data.
First Quarter 2009Agitated Leach Plant
During the first quarter of 2009, the Company installed a modified crushing/grinding system to the agitated leach plant. It is expected that with some additional modifications, the agitated leach plant will be fully operational toward the end of the third quarter of 2009.
The agitated leach plant is designed to increase production capacity from 1,000 tonnes of iodine per year to 1,500 tonnes per year.
read more... Production Results
Selected operational information for Aguas Blancas mine for the three months ended March 31, 2009 compared to 2008 is set out in the following table:
| |
Three months ended March 31, 2009
|
Three months ended December 31, 2008
|
Three months ended March 31, 2008 |
Operations |
|
|
|
Tonnes Mined metric tonnes (Mt) |
1,037,490 |
1,050,299 |
451,097 |
Iodine Grade (ppm) |
549 |
595 |
673 |
Iodine Produced (Mt) |
246 |
203 |
243 |
Iodine Sold (Mt) |
199 |
205 |
21 |
Tonnes of ore mined during the first quarter of 2009 were higher compared to the same period of 2008 in order to increase iodine production, noting that there is a delay of 3 to 4 months before ore to leach pads produces significant amounts of iodine. Iodine production during the first quarter of 2009 was impacted by operational downtime due to electrical power supply interruptions, solution pumps failure and heap leach solution system changes. These problems have been addressed and normal monthly production is expected to be achieved in the second quarter of 2009.
The Company will continue to focus on maintaining and increasing iodine production by optimizing heap leach operations while technical issues related to the conversion to the agitated leach plant are addressed.
Nitrate Fertilizer Project
The Company has temporarily deferred the development of the nitrate fertilizer plant due to the global credit crisis, the need to preserve cash and to focus on resolving the technical issues on the agitated leach plant.
Salvador Potash Project -- Brazil
Geophysics and geological work are underway for the selection and permitting of drill targets on the Salvador potash project. The Company expects to commence drilling in early third quarter of 2009.
RESULTS OF OPERATIONS
For the first quarter of 2009, the Company reported income from mining operations of $1.3 million
Year End 2008During 2008, the Company initiated the commissioning of a new agitated leach plant designed to replace the existing heap leaching system. As of the date of this report, the agitated leach plant is not yet operational. (See below section "Agitated Leach Plant and Power Supply").
As a result of the recent unprecedented events in the global financial markets and its adverse impact on the capital and debt markets, the Company has deferred all major capital expenditures, including the development of the nitrates fertilizer plant, that are not directly related to iodine production. See below section "Nitrate Fertilizer Project". The Company has also initiated comprehensive cost-saving measures in efforts to reduce production and administrative costs and preserve cash. Despite the crisis, iodine prices remained stable during 2008.
read more... 2008 HIGHLIGHTS
Agitated Leach Plant and Power Supply
During the second quarter of 2008, the Company initiated the commissioning of a new agitated leach plant designed to replace the existing heap leaching system. The agitated leach plant is expected to allow for a production increase to 1,500 metric tonnes ("Mt") per annum of prilled iodine from the current 1,000 Mt per annum level.
The Company encountered commissioning problems with the crushing/grinding section of the agitated leach plant, which was found to be inadequate for the caliche ore being processed. A modified scrubber designed to disaggregate and dissolve the ore while rejecting barren volcanic rocks without wasting energy on grinding was installed at an estimated cost of $1.5 million. The Company is currently commissioning the system.
It is expected that with some additional modifications to the scrubber, the agitated leach plant will be operational toward the end of the third quarter of 2009. Meanwhile, the Company has increased the amount of ore placed on the heap pads in order to increase iodine production until such time that the agitated leach plant is operational.
Projected total cost of the agitated leach plant, including the modifications to date and the additional scrubber system is currently estimated at $29.1 million of which $27.5 million has been spent to December 31, 2008.
In conjunction with the agitated leach plant, the Company completed a new powerline in April, 2008, connecting to the local power grid, replacing existing diesel generators. The total cost of the powerline was $7.8 million.
Production Results
Selected operational information for Aguas Blancas mine for the three and twelve months ended December 31, 2008 compared to 2007 is set out in the following table:
|
Three Months |
Three Months |
Year Ended |
Year Ended |
|
Ended December |
Ended December |
December |
December |
|
31, 2008 |
31, 2007 |
31, 2008 |
31, 2007 |
Tonnes Mined (Mt) |
1,050,299 |
975,148 |
2,592,083 |
4,097,838 |
Iodine Grade (ppm) |
595 |
520 |
659 |
518 |
Iodine Produced (Mt) |
203 |
253 |
844 |
1,075 |
Iodine Sold (Mt) |
205 |
234 |
861 |
1,095 |
Tonnes of ore mined during the year ended December 31, 2008 were lower compared to the same period of 2007 as a result of a new mine plan implemented in 2008 in anticipation of the commencement of the new agitated leach system with higher expected recoveries. However, due to the commissioning problems with the agitated leach plant, iodine production decreased for 2008 compared to the same period of 2007. In the fourth quarter of 2008, the Company increased the tonnes of mined ore to the heap leach pads in order to increase iodine production until such time the agitated leach plant is fully operational.
Nitrate Fertilizer Project
During the third quarter of 2008, the Company commenced with engineering and design of the nitrate fertilizer plant and continued with the construction of the solar evaporation ponds to harvest the nitrates salts to feed the plant. The plant is estimated to require an investment of $60 million and take approximately 27 months to complete and is designed to produce 70,000 tonnes of specialty nitrate fertilizers per year. Amounts spent on the nitrates plant and the solar evaporation ponds during the year ended December 31, 2008 were $0.8 million and $1.5 million, respectively. As a result of the technical problems with the agitated leach plant and the recent unprecedented global credit crisis, the Company has decided to temporarily defer the development of the nitrate fertilizer plant.
Salvador Potash Project -- Brazil
During the year ended December 31, 2008, the Company acquired exploration permits for the "Salvador Potash Project", located along the Atlantic coast of northeastern Brazil. Application has been made for additional exploration permits covering a total of 1,700 square kilometers west of the port city of Salvador, Bahia. Geophysics and geological work are underway for the selection and permitting of drill targets. The Company expects to commence drilling in the second quarter of 2009. The exploration budget for 2009 on the Salvador Potash Project is approximately $1.6 million.
Financing
In August 2008, the Company completed a brokered and non-brokered private placement of 50 million common shares of the Company at a price of CDN$1.00 per common share of gross proceeds of CDN$50 million. Finder's fees and other share issuance expenses totalling CDN$1.7 million were paid on a portion of the private
|